Articles Posted in Contracts
by
In 2006, the U.S. Army Contracting Agency solicited bids for repair, maintenance, and construction services at Fort Rucker, Alabama, with indefinite delivery and quantity terms. The mechanism for pricing such jobs involves identification of costs and multiplication by certain “coefficients” set in the contract. It was well known that construction costs in the region had increased after Hurricane Katrina, 15 months before the government solicited bids. The Army awarded the contract to Lakeshore in 2007. In 2008, Lakeshore began 78 construction projects at Fort Rucker. When the Army exercised its option to extend the contract, it increased payments based on the contract’s price-adjustment clause. Lakeshore began 74 more delivery orders. After two years under the contract, Lakeshore concluded that it had incurred higher costs than were covered by payments under the contract and requested an equitable adjustment. The government denied the request. Acting under the Contract Disputes Act, 41 U.S.C. 7101, the contracting officer denied a claim for recovery of $1,996,152.40. The Claims Court rejected claims of breach of contract, breach of the covenant of good faith and fair dealing, breach of implied warranty, and mistake on summary judgment, stating that the government was not obliged to provide accurate local prices or to bear “economic consequences if one or more prices in the guide proved inaccurate.” The Federal Circuit affirmed. View "Lakeshore Eng'g Servs., Inc. v. United States" on Justia Law

by
Endo sells Opana® ER extended-release tablets containing a painkiller, oxymorphone. In earlier litigation, Endo sued Roxane and Actavis for patent infringement, 35 U.S.C. 271(e)(2)(A), based on their Abbreviated New Drug Applications to market generic versions of Opana® ER. The lawsuits settled; Endo granted defendants a license and a covenant not to sue. After making the agreements the 122 and 216 patents issued to Endo. They are continuations of the same parent application and directed to extended-release oxymorphone compositions and methods of treating pain using those compositions. Endo also acquired the unrelated 482 patent, concerning purified oxymorphone compositions and methods of making those compositions. The asserted patents are listed in the Approved Drug Products with Therapeutic Equivalence Evaluations (Orange Book) entry for Opana® ER. Endo again sued for infringement and sought a preliminary injunction to prevent marketing or sales of generic oxymorphone formulations. The district court held that Endo was estopped from claiming that the activity of defendants, “which has gone on for a substantial period of time, is now suddenly barred because of these new patents.” The Federal Circuit vacated, finding that the defendants did not have an express or implied license to practice the patents at issue.View "Endo Pharm. Inc. v. Actavis, Inc." on Justia Law

by
Hauge and his former employer, ERI, disputed ownership of intellectual property rights related to “pressure exchangers,” a type of energy recovery device used in reverse osmosis. In 2001 they entered into an Agreement. The district court adopted the Agreement, holding that ERI was to be the sole owner of three U.S. patents and one pending patent application. After expiration of the Agreement’s non-compete clause, in 2004, Hauge filed a patent application, titled “Pressure Exchanger,” and a utility application. The patent issued in 2007, describing “[a] pressure exchanger for transferring pressure energy from a high-pressure fluid stream to low-pressure fluid stream.” In 2009, Hauge’s new company, Isobarix, unsuccessfully attempted to reach a new agreement with ERI. Isobarix began selling a pressure exchanger, called “XPR.” Hauge entered into a consulting agreement with two ERI employees. ERI sought an Order to Show Cause, in 2012, submitting an expert’s declaration that Isobarix was using pressure exchanger technology from pre-March 19, 2001 in design and manufacture of XPR, which is “virtually identical to the ERI pressure exchanger” in operation. The court entered a Contempt Order, finding that allowing Hauge to develop new products using technology he assigned to ERI solely because the new inventions post-date the Agreement would render the Agreement useless. The Federal Circuit vacated, finding that Hauge did not violate the “four corners” of the 2001 Order. View "Energy Recovery, Inc. v. Hauge" on Justia Law

by
The companies obtained an oil and gas lease from the government for a 5760-acre tract on the Outer Continental Shelf. They made an initial bonus payment of $23,236,314 and have paid additional rental payments of $54,720 per year. The lease became effective on August 1, 2008, and had an initial term running through July 31, 2016. It provided that it issued pursuant to and was subject to the Outer Continental Shelf Lands Act of August 7, 1953, (OCSLA) 43 U.S.C. 1331 and “all regulations issued pursuant to the statute in the future which provide for the prevention of waste and conservation of the natural resources of the Outer Continental Shelf and the protection of correlative rights therein; and all other applicable statutes and regulations.” In 2010, an explosion and fire on the Deepwater Horizon semi-submersible oil drilling rig in the Gulf of Mexico killed 11 workers and caused an oil spill that lasted several months. As a result, the government imposed new regulatory requirements, Oil Pollution Act (OPA), 33 U.S.C. 2701. The companies sued for breach of contract. The Claims Court and Federal Circuit ruled in favor of the government, finding that the government made the changes pursuant to OCSLA, not OPA. View "Century Exploration New Orleans, LLC v. United States" on Justia Law

by
In 2002 oil companies filed breach of contract actions against the government, concerning sales of offshore oil and glass leases in the 1980s. The Claims Court held that the government had breached its contracts by preventing the companies from drilling for oil in the offshore areas covered by the leases. The Federal Circuit affirmed the judgment and restitution awards of approximately $1 billion. Nycal, which held a 4.25 percent interest in two of the leases, waived its right to restitution and pursued a claim for lost profits. The Claims Court held that it was permissible for Nycal to seek lost-profits damages even though the other owners of the leases in which Nycal held a partial share had accepted restitution, but concluded that Nycal had not proved its case for lost profits. The Federal Circuit affirmed, noting the government’s evidence that Nycal could not have made a profit on its share of the leases.View "NYCAL Offshore Dev. Corp. v. United States" on Justia Law

by
In 2002, the Navy awarded Metcalf a contract to design and build 212 housing units in Hawaii by October, 2006, for $50 million. Problems arose involving soil conditions. The request for proposals stated that the “soil reconnaissance report” was “for preliminary information only” and required that the contractor conduct independent soil investigation, incorporating 48 C.F.R. 52.236-2, concerning site conditions that differ materially from those disclosed. Discussions delayed construction for a year. Metcalf implemented its preferred changes by over-excavating and using non-expansive fill, without a contract modification. The Navy denied that there was any material difference between pre-bid and post-award soil assessments, but approved some modifications. Metcalf was about 200 days behind schedule and began using “post-tension” concrete, which was more expensive but avoided the additional time and cost of over-excavation. The Navy amended the contract to approve use of post-tension concrete slabs. Metcalf claims additional delays resulting from the presence of more of a chemical contaminant than was expected. With respect to contamination, the Navy granted a 286-day extension and reimbursed $1,493,103. The Navy accepted the buildings in March, 2007. Metcalf alleged that its final cost was $76 million. The government paid less than $50 million. The Claims Court ruled in favor of the government, under the Contract Disputes Act, 41 U.S.C. 7104. The Federal Circuit vacated, holding that the court misconstrued what Metcalf needed to show to prove that the government breached its duty of good faith and fair dealing and misinterpreted certain contractual provisions.View "Metcalf Const. Co., LLC v. United States" on Justia Law

by
Crewzers was awarded blanket purchase agreements (BPAs) with the Forest Service to provide buses that transport fire crews to wildfires and other disaster areas in regional and national wilderness zones and to provide flame retardant tents to disaster areas. Both BPAs established dispatch priority lists within geographic zones. When an emergency arose, the Service would to submit an order for the highest-ranked (lowest-priced) resource available on the priority. BPAs are frameworks for future contracts and state that “If a Contractor cannot be reached or is not able to meet the time and date needed, the dispatcher may proceed with contacting the next resource on the dispatch priority list.” The Service has discretion to deviate from priority lists as needed and did not make any guarantee that it would actually place orders under the BPAs. The BPAs required Crewzers to accept orders only if “willing and able.” The Service terminated the Crewzers BPA for buses after Crewzers allegedly responded with unauthorized vehicles and attempted to bill at a higher-than-authorized rate and later terminated its BPA for tents after Crewzers allegedly provided tents that did not meet specifications or failed to deliver on time. Crewzers sought a declaratory judgment that it was entitled to damages or to reinstatement of the BPAs. The Claims Court dismissed. The Federal Circuit affirmed, finding that the BPAs were not binding contracts for purposes of invoking Tucker Act (28 U.S.C. 1491(a)) jurisdiction. View "Crewzers Fire Crew Transp., Inc. v. United States" on Justia Law

by
In 2001 KBR agreed to provide the Army with logistics support services during Operation Iraqi Freedom. Individual task orders required KBR to install, operate and maintain dining services near Mosul, Iraq on a cost-plus-award-fee basis. KBR selected ABC, a subcontractor, to build a prefabricated metal dining facility and to provide dining services for a camp population of 2,573. In June 2004, the Army ordered KBR to stop construction of the metal facility and begin construction of a reinforced concrete facility for an estimated 2,573 to 6,200+ persons. Instead of requesting bids for the new work, KBR kept ABC as the subcontractor due to the urgency of the request. ABC submitted a new proposal with a total monthly cost about triple the monthly cost initially quoted. ABC attributed the increased costs to additional labor and equipment to serve a larger population and to a drastic increase in the cost of labor and a severe shortage of staff willing to work in Iraq. Due to a calculation error, it was determined that ABC’s proposal was reasonable. KBR’s management reviewed and approved a change order, embodying ABC’s proposal. In 2005 the subcontract ended and title to the dining facility passed to the Army. In 2007, the Defense Contract Auditing Agency suspended payment of certain costs paid by KBR to ABC pursuant to the change order. KBR prepared a new price justification for the concrete dining facility and ultimately filed suit, seeking recovery of the $12,529,504 in costs disapproved for reimbursement. The Claims Court awarded $6,779,762. The Federal Circuit affirmed.View "Kellogg Brown & Root Servs. v. United States" on Justia Law

by
In 2006, the Federal Bureau of Prisons issued a Request for Proposals for the “design-build” construction of a federal correctional institution. The project involved a “cut-to-fill” site, meaning that the ground had to be leveled by excavating materials from one area of the site and using those materials to fill lower areas. Based on information in the solicitation documents and prior experience, BH believed the New Hampshire Department of Environmental Sciences would approve a permit for a one-step-cut-to-fill construction plan and calculated its bid price, $238,175,000, accordingly. The contract provided liquidated damages of $8,000 for each day completion was overdue. The NHDES rejected the application. BH advised the government of the implications of NHDES restrictions, but did not refuse to proceed or request that the government intervene with the NHDES. According to BH, the restrictions were contrary to generally accepted industry practice. Upon completion of cut-to-fill operations, BH submitted a Request for Equitable Adjustment, seeking $7,724,885 for excess costs. The Contracting Officer and the Claims Court rejected the request, finding that the Permits and Responsibilities clause placed the burden of obtaining and complying with state and local permits on BH “without additional expense to the Government;” that BH had not alleged violation of the implied duty of good faith; and that, because the government did not control the NHDES, there was no basis for imposing liability for constructive change. The Federal Circuit affirmed. View "Bell/Heery v. United States" on Justia Law

by
Access sells software for mobile communication, owns the patents at issue, and entered into an exclusive license agreement with APAC, a subsidiary of Acacia. The agreement gave APAC the exclusive right to grant sublicenses, to sue for damages and to seek relief for infringement of the patents. The agreement disclaims third-party-beneficiary rights, states that APAC may not enforce the patents against, or seek licenses to practice the patents from, Access’s customers and end-users in connection with Access’s products and services, and states that APAC and Access consent to the exclusive jurisdiction of any California state or federal court. APAC assigned all of its rights and liabilities in the patents to a wholly owned subsidiary, SmartPhone. SmartPhone sued Huawei, which makes mobile handsets and tablets, in Texas, alleging that Huawei products infringe the patents. Huawei then sued SmartPhone, Acacia Research, and Access in California, alleging that Huawei has been an Access customer for more than 10 years and seeking declaratory judgments of noninfringement. Based on the Texas filing, the district court dismissed the noninfringement and invalidity counts under the first-to-file rule. Dismissing remaining counts, the court stated that.an allegation that the parties intended Huawei to benefit from the license agreement conflicted with its terms. The Federal Circuit affirmed. View "Futurewei Tech., Inc. v. Acacia Research Corp." on Justia Law