Justia U.S. Federal Circuit Court of Appeals Opinion Summaries

Articles Posted in Contracts
by
In 2008 the district court calculated damages for the government's partial breach of the Standard Contract for disposal of spent nuclear fuel using the 1991 Annual Capacity Report and the duty of good faith and fair dealing. The Federal Circuit, having set the 1987 ACR as the appropriate acceptance rate for a causation analysis under the Standard Contract, remanded. On remand, the district court set the amount of damages at $89,004,415. The Federal Circuit affirmed, holding that the new judgment accounts for the proper causation times and principle. View "Pacific Gas & Elec. Co. v. United States" on Justia Law

by
Plaintiff alleged infringement of patents covering systems and devices for testing blood samples against a competitor in the diagnostic field. The patents at issue name defendant as the assignee. Plaintiff claimed ownership based on confidentiality and non-competition clauses in employment and consulting contracts between its predecessor and an employee, the inventor. The district court dismissed, finding that plaintiff lacked standing because the 1999 Consulting Agreement did not continue the 1984 Agreement’s Disclosure and Assignment Covenant. The Federal Circuit affirmed, holding that the company lacked standing with respect to rights assigned long after the inventor resigned from the company. View "Abbott Point of Care, Inc. v. Epocal, Inc." on Justia Law

by
Plaintiff, which owned a nuclear power plant, entered into the standard U.S. Department of Energy contract, under which DOE agreed to collect spent nuclear fuel (SNF) no later than 1998. DOE never began collecting SNF and has breached contracts nationwide. Massachusetts restructured the electric utility industry and, in 1999, the plant sold for $80 million; buyer agreed to accept decommissioning responsibilities for $428 million. The district court awarded $40 million for the portion of the decommissioning fund corresponding to projected post-decommissioning SNF-related costs attributable to DOE’s continuing breach. The court awarded the buyer $4 million in mitigation damages, including direct and overhead costs for new spent fuel racks and fees paid to the NRC. The Federal Circuit reversed in part and remanded. Plaintiff cannot recover damages under a diminution-of-value theory in a partial breach setting. The sale of assets does not alter the principle that when the breaching party has not repudiated and is still expected to perform, anticipated damages are not recoverable until incurred. A non-breaching party may recover from the government indirect overhead costs associated with mitigation and the costs of financing those activities.

by
The 2008 Medicare Improvements for Patients and Providers Act, 42 U.S.C. 1395w-3, unilaterally terminated a number of medical equipment and supplies contracts that had been made previously with individual providers by the government and purported to deny an "independent" cause of action or right to administrative or judicial review with regard to the terminations The court of claims dismissed a suit by plaintiff, whose contracts were terminated. The Federal Circuit reversed, noting several possible interpretations of the peculiar wording of the provision. The Act not withdraw traditional contract jurisdiction under the Tucker Act, 28 U.S.C 1491(a)(1) and plaintiff stated a claim.

by
In 2003, the company entered into contracts with the government for roof repairs of two government buildings. Due to delays the projects were not completed and accepted by the government until September and October 2005. At the time, Federal Acquisition Regulations required that a performance report be prepared for each construction contract for $550,000 or more, 48 C.F.R. § 36.201. The company received negative interim performance evaluations from the resident engineer for both projects in February, 2004. In March, 2006, the resident engineer issued proposed negative final performance evaluations for both projects. The company protested the proposed evaluations, asserting that subcontractors and other problems, beyond its control, caused the delays. In final performance evaluations, the engineer assigned an overall performance rating of unsatisfactory and assigned unsatisfactory ratings for each project in 15 individual categories. The contracting officer issued a final decision that the unsatisfactory performance appraisal was justified. The Claims Court rejected the company's suit. The Federal Circuit affirmed. A contractor is responsible for the unexcused performance failures of its subcontractors and the complaint did not allege facts that would excuse the delays.

by
In 1983, Congress enacted the Nuclear Waste Policy Act, authorizing contracts with nuclear plant utilities, generators of spent nuclear fuel (SNF) and high-level radioactive waste (HWL) under which the gVovernment would accept and dispose of nuclear waste in return for the generators paying into a Nuclear Waste Fund, 42 U.S.C. 10131. In 1983, the Department of Energy entered into the standard contract with plaintiff to accept SNF and HLW. In 1987, Congress amended the NWPA to specify that the repository would be in Yucca Mountain, Nevada. The government has yet to accept spent fuel. The current estimate is that the government will not begin accepting waste until 2020, if at all. In 2001, plaintiff began constructing dry storage facilities to provide on-site storage for SNF rather than to continue using an outside company (ISFSI project). The Court of Federal Claims awarded $142,394,294 for expenses due to DOE’s breach; 23,657,791 was attributable to indirect overhead costs associated with the ISFSI project. The Federal Circuit affirmed. Breach of the standard contract caused plaintiff to build, staff, and maintain an entirely new facility; the ISFSI facilities had not existed prior to the breach and were necessitated by the breach.

by
The U.S. Department of Energy breached its agreement to accept spent nuclear fuel from nuclear power utilities, including plaintiff, a Wisconsin power cooperative, no longer in operation. Plaintiff maintains 38 metric tons of spent uranium on its property. Had DOE not breached the agreement, the material would have been removed in 2006. Plaintiff joined a consortium of 11 utilities to develop a private repository. The district court awarded about $37.6 million: $16.6 million for maintaining the fuel on-site from 1998 to 2006, $12 million for investment in the consortium, and $6.1 million for various overhead costs associated with mitigation. The Federal Circuit vacated in part. The claims court properly determined that plaintiff was entitled to damages for the entire period, 1999-2006; properly awarded overhead; properly offset the consortium costs; but should have limited the award with respect to the consortium to expenses incurred for mitigation.

by
The Department of Justice issued a request for quotations for an automated recruiting and staffing system, providing that conflicting provisions would be considered as exceptions to the terms of the RFQ, and noting that any exceptions could adversely impact the evaluation rating. Plaintiff's bid included exceptions relating to confidentiality of data and how payments would be made, among other matters. Plaintiff's program obtained a higher score on a performance test. The DOJ disqualified plaintiff's bid and accepted intervenor's bid, stating that plaintiff's slight technical advantage did not justify the higher price and that plaintiff's exceptions were unacceptable. The government accountability office, claims court, and Federal Circuit upheld the decision. The contracting officer was not required to engage in discussions about the exceptions before disqualifying the bid and acted rationally in disqualifying the bid. The officer was entitled to rely on a certification of compliance with RFQ terms for the bid that was accepted and rationally accepted that bid.

by
The U.S. Department of Energy entered into standard contracts to accept spent nuclear fuel from utility companies by January 1998 and has not yet accepted delivery, resulting in suits by several nuclear utilities. The district court awarded Dominion damages. The Federal Circuit affirmed, first holding that the Nuclear Waste Policy Act, 42 U.S.C. 10222, permitted assignment by Dominion's predecessor, that the assignment complied with the Act and the contract, and that the assignment included the right to pre-assignment damages. The district court properly denied discovery on the government's claim that Dominion has benefited from its breach because it has not yet been required to pay a one-time fee for disposal of waste generated prior to 1983.

by
The owner of patents for computer modems and methods of identifying modems licensed the patents to Rockwell; a related agreement gave Rockwell sub-licensing rights. Rockwell reorganized and assigned its rights. The patent owner acknowledged the assignment. Defendants obtain modem chips from a "spin off" of the companies formed in the Rockwell reorganization. The patent owner sued for infringement. The district court held that the defendants are licensed and entered summary judgment that certain patents are invalid. The Federal Circuit reversed in part, first holding that the assignment was within Rockwell's sub-licensing rights without further consent. Two patent claims were invalid for indefiniteness, but there was a material issue of fact on whether two others were invalid for failure to disclose necessary algorithms.