Justia U.S. Federal Circuit Court of Appeals Opinion Summaries
Articles Posted in Contracts
VT Yankee Nuclear Power Corp. v. United States
In 1983, the Nuclear Waste Policy Act, 42 U.S.C. 10101-10270, authorized the Department of Energy to contract with nuclear facilities for disposal of spent nuclear fuel and high level radioactive waste. The Standard Contract provided that rights and duties may be assignable with transfer of SNF title. Plaintiff entered into the Standard Contract in 1983 and sold its operation and SNF to ENVY in 2002, including assignment of the Standard Contract, except one payment obligation. Plaintiff transferred claims related to DOE defaults. As a result of DOE’s breach, ENVY built on-site dry-storage facilities. The Claims Court consolidated ENVY’s suit with plaintiff’s suit. The government admitted breach; the Claims Court awarded ENVY $34,895,467 (undisputed damages) and certain disputed damages. The Federal Circuit affirmed in part. Plaintiff validly assigned pre-existing claims; while partial assignment of rights and duties under the contract was not valid, the government waived objection. The assignment encompassed claims against the government. Legal and lobbying fees to secure Vermont approval for mitigation were foreseeable, but other expenses were not recoverable. ENVY failed to prove costs of disposing of contaminated material discovered due to the breach and its characterization of spent fuel moved to dry storage. ENVY is not entitled to recover cost of capital for funding mitigation, or Resource Code 19 payroll loader overhead costs, but may recover capital suspense loader overhead costs,.View "VT Yankee Nuclear Power Corp. v. United States" on Justia Law
FloorPro, Inc. v. United States
In February, 2002, the Navy awarded GM&W a contract for floor coating at a military base. GM&W subcontracted with FloorPro, which completed the work on February 27, 2002 and billed GM&W. On March 8, the Navy informed GM&W that the work was completed satisfactorily. On April 17, FloorPro informed the Navy’s contracting officer that it had not been paid. GM&W had claims pending and was not sure whether funds that the Navy directly deposited would be available to FloorPro. In April 2002, the Navy and GM&W entered into contract modification providing for mailing to FloorPro of a check payable to GM&W and Floor-Pro. The Navy paid GM&W directly by electronic transfer and informed FloorPro that its recourse was to sue GM&W. In December 2002, FloorPro submitted a claim to the Navy’s contracting officer. On March 27, 2003, FloorPro filed at the Armed Services Board of Contract Appeals, which awarded $37,500. The Federal Circuit reversed, holding that under the Contract Disputes Act, 41 U.S.C. 7101, ASBCA has no jurisdiction over a claim by a subcontractor. In 2009, FloorPro filed in the Court of Claims, which ruled in favor of FloorPro. The Federal Circuit vacated, ordering dismissal under the six-year limitations period of 28 U.S.C. 2501. View "FloorPro, Inc. v. United States" on Justia Law
Consol. Edison Co. of NY, Inc. v. United States
In 1983, Congress enacted the Nuclear Waste Policy Act, 42 U.S.C. 10101-10270, authorizing the Department of Energy to enter into contracts with nuclear facilities for the disposal of spent nuclear fuel (SNF) and high-level radioactive waste (HLW). Congress mandated that, under the Standard Contract, DOE dispose of SNF and HLW beginning not later than January 31, 1998. In 1983, DOE entered into a Standard Contract with Consolidated Edison under which DOE agreed to accept SNF stored at the Indian Point facility. Following DOE’s breach, the Claims Court awarded two categories of damages: wet storage costs for continued operation of its Unit 1 spent fuel pool and regulatory fees paid to the U.S. Nuclear Regulatory Commission. The Federal Circuit reversed the awards, affirmed denial of damages for the cost of financing mitigation activities, but reversed denial of damages for indirect overhead costs associated with mitigation. The company had chosen to prioritize removal of Unit 2 SNF and Unit 1 material would not have been removed by the time at issue; the company did not establish that the breach caused an increase in fees to the NRC. View "Consol. Edison Co. of NY, Inc. v. United States" on Justia Law
VanDesande v. United States
Plaintiff entered into a "Stipulation Agreement Regarding Damages," approved by the EEOC, to resolve her Title VII pregnancy discrimination claim against the U.S. Postal Service. She later filed suit in the Court of Federal Claims, alleging breached of that Agreement. The court held that it did not have jurisdiction because the Agreement was a consent decree, not a contract. In the federal system, when the United States is the defendant, whether the issue is enforcement of a court decree by the issuing forum or enforcement of a settlement contract in a separate suit determines which court can hear the case. The Federal Circuit reversed, stating that the "dispute is yet another example of the wastefulness of litigation over where to litigate." Consent decrees and settlement agreements are not necessarily mutually exclusive; a settlement agreement, even one embodied in a decree, is a contract within the meaning of the Tucker Act. View "VanDesande v. United States" on Justia Law
Minesen Co. v. McHugh
The company has been under contract with the U.S. Army’s Morale, Welfare, and Recreation Fund since 1993 to build and operate a hotel at a military base on Oahu. With 18 years remaining on the agreement, the Armed Services Board of Contract Appeals determined that the Fund breached the core of the contract and the parties entered the damages phase of the dispute. The company filed a separate complaint alleging that the Fund had done nothing to cure its ongoing breach. The ASBCA dismissed the second complaint as duplicative. The Federal Circuit affirmed, finding that the company voluntarily waived its right to appeal to the court under its negotiated contract with the Fund.
View "Minesen Co. v. McHugh" on Justia Law
Pacific Gas & Elec. Co. v. United States
In 2008 the district court calculated damages for the government's partial breach of the Standard Contract for disposal of spent nuclear fuel using the 1991 Annual Capacity Report and the duty of good faith and fair dealing. The Federal Circuit, having set the 1987 ACR as the appropriate acceptance rate for a causation analysis under the Standard Contract, remanded. On remand, the district court set the amount of damages at $89,004,415. The Federal Circuit affirmed, holding that the new judgment accounts for the proper causation times and principle. View "Pacific Gas & Elec. Co. v. United States" on Justia Law
Abbott Point of Care, Inc. v. Epocal, Inc.
Plaintiff alleged infringement of patents covering systems and devices for testing blood samples against a competitor in the diagnostic field. The patents at issue name defendant as the assignee. Plaintiff claimed ownership based on confidentiality and non-competition clauses in employment and consulting contracts between its predecessor and an employee, the inventor. The district court dismissed, finding that plaintiff lacked standing because the 1999 Consulting Agreement did not continue the 1984 Agreement’s Disclosure and Assignment Covenant. The Federal Circuit affirmed, holding that the company lacked standing with respect to rights assigned long after the inventor resigned from the company. View "Abbott Point of Care, Inc. v. Epocal, Inc." on Justia Law
Boston Edison Co. v. United States
Plaintiff, which owned a nuclear power plant, entered into the standard U.S. Department of Energy contract, under which DOE agreed to collect spent nuclear fuel (SNF) no later than 1998. DOE never began collecting SNF and has breached contracts nationwide. Massachusetts restructured the electric utility industry and, in 1999, the plant sold for $80 million; buyer agreed to accept decommissioning responsibilities for $428 million. The district court awarded $40 million for the portion of the decommissioning fund corresponding to projected post-decommissioning SNF-related costs attributable to DOE’s continuing breach. The court awarded the buyer $4 million in mitigation damages, including direct and overhead costs for new spent fuel racks and fees paid to the NRC. The Federal Circuit reversed in part and remanded. Plaintiff cannot recover damages under a diminution-of-value theory in a partial breach setting. The sale of assets does not alter the principle that when the breaching party has not repudiated and is still expected to perform, anticipated damages are not recoverable until incurred. A non-breaching party may recover from the government indirect overhead costs associated with mitigation and the costs of financing those activities.
Cardiosom, L.L.C. v. United States
The 2008 Medicare Improvements for Patients and Providers Act, 42 U.S.C. 1395w-3, unilaterally terminated a number of medical equipment and supplies contracts that had been made previously with individual providers by the government and purported to deny an "independent" cause of action or right to administrative or judicial review with regard to the terminations The court of claims dismissed a suit by plaintiff, whose contracts were terminated. The Federal Circuit reversed, noting several possible interpretations of the peculiar wording of the provision. The Act not withdraw traditional contract jurisdiction under the Tucker Act, 28 U.S.C 1491(a)(1) and plaintiff stated a claim.
Todd Constr., L.P. v. United States
In 2003, the company entered into contracts with the government for roof repairs of two government buildings. Due to delays the projects were not completed and accepted by the government until September and October 2005. At the time, Federal Acquisition Regulations required that a performance report be prepared for each construction contract for $550,000 or more, 48 C.F.R. § 36.201. The company received negative interim performance evaluations from the resident engineer for both projects in February, 2004. In March, 2006, the resident engineer issued proposed negative final performance evaluations for both projects. The company protested the proposed evaluations, asserting that subcontractors and other problems, beyond its control, caused the delays. In final performance evaluations, the engineer assigned an overall performance rating of unsatisfactory and assigned unsatisfactory ratings for each project in 15 individual categories. The contracting officer issued a final decision that the unsatisfactory performance appraisal was justified. The Claims Court rejected the company's suit. The Federal Circuit affirmed. A contractor is responsible for the unexcused performance failures of its subcontractors and the complaint did not allege facts that would excuse the delays.