Justia U.S. Federal Circuit Court of Appeals Opinion Summaries

Articles Posted in Contracts
by
In 1983, Congress enacted the Nuclear Waste Policy Act, authorizing contracts with nuclear plant utilities, generators of spent nuclear fuel (SNF) and high-level radioactive waste (HWL) under which the gVovernment would accept and dispose of nuclear waste in return for the generators paying into a Nuclear Waste Fund, 42 U.S.C. 10131. In 1983, the Department of Energy entered into the standard contract with plaintiff to accept SNF and HLW. In 1987, Congress amended the NWPA to specify that the repository would be in Yucca Mountain, Nevada. The government has yet to accept spent fuel. The current estimate is that the government will not begin accepting waste until 2020, if at all. In 2001, plaintiff began constructing dry storage facilities to provide on-site storage for SNF rather than to continue using an outside company (ISFSI project). The Court of Federal Claims awarded $142,394,294 for expenses due to DOE’s breach; 23,657,791 was attributable to indirect overhead costs associated with the ISFSI project. The Federal Circuit affirmed. Breach of the standard contract caused plaintiff to build, staff, and maintain an entirely new facility; the ISFSI facilities had not existed prior to the breach and were necessitated by the breach.

by
The U.S. Department of Energy breached its agreement to accept spent nuclear fuel from nuclear power utilities, including plaintiff, a Wisconsin power cooperative, no longer in operation. Plaintiff maintains 38 metric tons of spent uranium on its property. Had DOE not breached the agreement, the material would have been removed in 2006. Plaintiff joined a consortium of 11 utilities to develop a private repository. The district court awarded about $37.6 million: $16.6 million for maintaining the fuel on-site from 1998 to 2006, $12 million for investment in the consortium, and $6.1 million for various overhead costs associated with mitigation. The Federal Circuit vacated in part. The claims court properly determined that plaintiff was entitled to damages for the entire period, 1999-2006; properly awarded overhead; properly offset the consortium costs; but should have limited the award with respect to the consortium to expenses incurred for mitigation.

by
The Department of Justice issued a request for quotations for an automated recruiting and staffing system, providing that conflicting provisions would be considered as exceptions to the terms of the RFQ, and noting that any exceptions could adversely impact the evaluation rating. Plaintiff's bid included exceptions relating to confidentiality of data and how payments would be made, among other matters. Plaintiff's program obtained a higher score on a performance test. The DOJ disqualified plaintiff's bid and accepted intervenor's bid, stating that plaintiff's slight technical advantage did not justify the higher price and that plaintiff's exceptions were unacceptable. The government accountability office, claims court, and Federal Circuit upheld the decision. The contracting officer was not required to engage in discussions about the exceptions before disqualifying the bid and acted rationally in disqualifying the bid. The officer was entitled to rely on a certification of compliance with RFQ terms for the bid that was accepted and rationally accepted that bid.

by
The U.S. Department of Energy entered into standard contracts to accept spent nuclear fuel from utility companies by January 1998 and has not yet accepted delivery, resulting in suits by several nuclear utilities. The district court awarded Dominion damages. The Federal Circuit affirmed, first holding that the Nuclear Waste Policy Act, 42 U.S.C. 10222, permitted assignment by Dominion's predecessor, that the assignment complied with the Act and the contract, and that the assignment included the right to pre-assignment damages. The district court properly denied discovery on the government's claim that Dominion has benefited from its breach because it has not yet been required to pay a one-time fee for disposal of waste generated prior to 1983.

by
The owner of patents for computer modems and methods of identifying modems licensed the patents to Rockwell; a related agreement gave Rockwell sub-licensing rights. Rockwell reorganized and assigned its rights. The patent owner acknowledged the assignment. Defendants obtain modem chips from a "spin off" of the companies formed in the Rockwell reorganization. The patent owner sued for infringement. The district court held that the defendants are licensed and entered summary judgment that certain patents are invalid. The Federal Circuit reversed in part, first holding that the assignment was within Rockwell's sub-licensing rights without further consent. Two patent claims were invalid for indefiniteness, but there was a material issue of fact on whether two others were invalid for failure to disclose necessary algorithms.

by
In 1983 the Department of Energy contracted to dispose of spent nuclear fuel from plaintiff's Columbia, Washington facility. The DOE failed to perform and, with its own temporary storage filling up, the plaintiff began work on its own permanent storage facility in 2002. The trial court award of $56.9 million included amounts for modifications to the temporary storage facility, indirect overhead, and financing costs. The Federal Circuit vacated. The plaintiff was entitled to damages for modifications only to the extent that it could prove that, but for the breach, those costs would not have been incurred; the trial court did not require the plaintiff to prove causation. The trial court properly included an award for indirect overhead calculated to a reasonable certainty. The government was entitled to sovereign immunity (28 U.S.C. 2516) with respect to the award of $6 million in interest; the contract did not waive immunity.