DEXCOM, INC. v. ABBOTT DIABETES CARE, INC.
This case revolves around an interlocutory appeal from a consolidated case between Abbott Diabetes Care, Inc., Abbott Diabetes Care Sales Corp. (collectively, “Abbott”), and DexCom, Inc. at the United States District Court for the District of Delaware. DexCom had sued Abbott for infringing its patents, leading Abbott to petition for inter partes review of the asserted patents before the Patent Trial and Appeal Board. DexCom sought a preliminary injunction to prevent Abbott from proceeding with the inter partes review proceedings based on a forum selection clause in a settlement and license agreement between the parties. DexCom appealed the district court’s denial of the preliminary injunction.The United States Court of Appeals for the Federal Circuit affirmed the district court's decision, holding that the district court did not abuse its discretion in denying the preliminary injunction. The court found that the forum selection clause in the settlement and license agreement did not preclude the filing of inter partes review petitions after the Covenant Period because it allowed them during the Covenant Period. Therefore, DexCom could not succeed on its breach-of-contract counterclaim, making it ineligible for a preliminary injunction. View "DEXCOM, INC. v. ABBOTT DIABETES CARE, INC. " on Justia Law
NOVA GROUP/TUTOR-SALIBA v. US
In this case, Nova Group/Tutor-Saliba (“NTS”) was awarded a construction contract by the United States Department of the Navy to build a new aircraft carrier maintenance pier at a naval base. The contract required NTS to demolish an old pier, design and build a replacement pier, and construct a new structure known as the Mole Quaywall, which would be designed by the government. During construction, NTS encountered unexpected subsurface soil conditions that complicated and increased the cost of the project. NTS sought additional compensation from the government alleging differing site conditions.The United States Court of Appeals for the Federal Circuit affirmed the decision of the United States Court of Federal Claims which had denied NTS's claim for additional compensation. The Court of Federal Claims found that NTS had not established a Type I differing site condition because the contract documents disclosed that NTS would encounter unpredictable subsurface conditions and possible obstructions. It also found that NTS had failed to prove a Type II differing site condition, as it had not demonstrated that any of the potential causes for hard driving were unknown or unusual in the region or materially different from comparable work. The Court of Appeals agreed with these findings and also ruled that the parol evidence rule had not been violated as NTS claimed. The Court of Appeals found that the parol evidence rule does not prevent a party from presenting evidence that a recital of fact in an integrated agreement may be untrue, and the challenged evidence was not introduced to modify any term of the contract. Therefore, the appeal by NTS was denied and the decision of the Court of Federal Claims was affirmed. View "NOVA GROUP/TUTOR-SALIBA v. US " on Justia Law
Department of Transportation v. Eagle Peak Rock & Paving, Inc.
The Department of Transportation’s Federal Highway Administration (FHWA) contracted with Eagle for construction work in Yellowstone National Park, to be completed by October 2018. The contract required Eagle to submit a schedule detailing how it would complete the project on time. By late January 2017, FHWA had rejected Eagle’s eight formal schedule submissions as not complying with the contract. In February 2017, the contracting officer terminated the contract for default, concluding that Eagle was insufficiently likely to complete the project on time.Eagle challenged the termination for default under the Contract Disputes Act of 1978 (CDA), 41 U.S.C. 7101–7109, before the Civilian Board of Contract Appeals, which ruled that the termination for default was improper. The Board converted the termination to one for the convenience of the government, relying heavily, though not exclusively, on its view of deficiencies in the contracting officer’s reasoning, rather than on de novo findings about whether the record developed before the Board showed that standard for termination for default was met. The Federal Circuit vacated and remanded for the Board to adjudicate the case de novo. The Board’s evaluation of the contracting officer’s reasoning exceeded the limited scope of the threshold inquiry. The Board also failed to separate that threshold analysis from its de novo evaluation of the evidence. View "Department of Transportation v. Eagle Peak Rock & Paving, Inc." on Justia Law
Lockheed Martin Aeronautics Co. v. Secretary of the Air Force
For pressing projects, the government can issue “Undefinitized Contract Actions” (UCAs) to allow contractors to begin work before the parties have reached a final agreement on contract terms, like price. The Air Force entered into two UCAs with Lockheed for upgrades to F-16 aircraft. Both UCAs include “definitization” clauses that provide that if the parties are unable to reach agreements on price by a certain time, the Contracting Officer (CO) may determine a reasonable price. After years of negotiations, the Air Force and Lockheed were unable to agree on the price terms. The CO assigned to each UCA unilaterally definitized a price of about $1 billion.The Armed Services Board of Contract Appeals (ASBCA), acting under the Contract Disputes Act (CDA), dismissed appeals for lack of jurisdiction because Lockheed failed to submit a certified contractor claim to the COs requesting a final decision on its claims as required under the CDA. The Federal Circuit affirmed, rejecting Lockheed’s argument that the COs’ unilateral definitizations qualified as government claims under the CDA, which a contractor can directly appeal to the ASBCA without having to submit its own claim to the COs. The COs’ definitizations of the contract prices were not demands or assertions by the government seeking relief against Lockheed. View "Lockheed Martin Aeronautics Co. v. Secretary of the Air Force" on Justia Law
Roman v. United States
In their divorce settlement, Roman gave Iris $150,000. Iris transferred to Roman her interest in their home. Roman agreed to pay any taxes assessed on Iris for her receipt of the $150,000. The IRS assessed $50,002.04 in taxes and penalties and mailed her a notice of intent to take possession of her property, including the home. Although Iris no longer had any ownership rights in the home and no lien had been placed, an IRS employee stated that the tax liability must be paid to stop a levy against Roman’s home and that Roman could appeal once the tax was paid. Roman apparently believed that he had no alternative to paying "a tax that he did not owe.” An installment agreement listed Iris as the taxpayer, identifying Roman’s checking account. Roman did not sign the agreement but sent the IRS payments until the obligation was satisfied.Roman sought a refund, arguing that under 26 U.S.C. 121(a) his payment to Iris qualified for an exclusion from gross income of gain for certain sales of a principal residence. The Federal Circuit vacated Roman’s award. Roman was not a “taxpayer” under 26 U.S.C. 6511(a), so the Claims Court lacked jurisdiction to hear Roman’s third-party refund claim under section 1346(a)(1). Roman nevertheless pled a claim under 28 U.S.C. 1491(a)(1); a party who pays a tax for which he is not liable may sue to recover that tax if it was paid under duress. View "Roman v. United States" on Justia Law
Supreme Foodservice GmbH v. Director of the Defense Logistics Agency
In 2005, the Defense Logistics Agency (DLA) awarded Supreme a contract to provide food to U.S. forces in Afghanistan. During negotiations concerning deliveries to forward operating bases, Supreme submitted inflated cost proposals. Supreme threatened to withhold payments to subcontractors (potentially cutting off supplies to troops), The parties executed a Modification, including Supreme’s proposed rates, subject to verification. The Defense Contract Audit Agency concluded that Supreme’s documentation was not adequate and questioned more than $375 million of claimed costs. The contracting officer, in 2011, determined that DLA had overpaid Supreme by $567,267,940. DLA withheld $540 million from Supreme’s monthly payments. Supreme submitted unsuccessful “reverse image” claims. In 2014, Supreme pled guilty to fraud and entered into a civil settlement in a False Claims Act suit. During the investigations, with Supreme’s contract expiring, the parties entered into two extensions. In 2015, based on Supreme’s guilty plea, DLA demanded the return of all money paid under the contract. In 2020, the Armed Services Board of Contract Appeals concluded that Supreme’s contract claims against the government were barred by Supreme’s prior material breach.The Federal Circuit affirmed. The government did not waive its prior material breach defense. While DLA had some notice of Supreme’s fraudulent behavior in 2009, it had no “known right” until Supreme’s guilty plea, after which DLA never extended Supreme’s contract. Supreme cannot treat the bridge contracts as separate only to evade the government’s affirmative defenses. The parties treated the original contract and the extensions as inextricably intertwined; DLA’s prior material breach defense applies to those contracts. View "Supreme Foodservice GmbH v. Director of the Defense Logistics Agency" on Justia Law
Uniloc 2017 LLC v. Google LLC
Uniloc brought multiple infringement suits against Google concerning patents directed to innovations in multimedia content delivery, IT security, high-resolution imaging, network connectivity, video conferencing, and image and text searching. Google alleged Uniloc lacked standing because its predecessors had granted Fortress a license and an unfettered right to sublicense to the asserted patents as part of a financing arrangement. Uniloc argued that any license had been eliminated by a Termination Agreement executed between Uniloc’s predecessors and Fortress before the suits commenced.The district court dismissed, finding that a license had been granted and survived the Termination Agreement. The Federal Circuit reversed. The district court erred in interpreting the Termination Agreement. The License Agreement granted Fortress a “non-exclusive, transferrable, sub-licensable, divisible, irrevocable, fully paid-up, royalty-free and worldwide license” to several of Uniloc’s patents, including those at issue. The Termination Agreement stated that the License Agreement “shall terminate and shall be of no further force or effect without any further documentation or action and without liability to any party hereto, and the rights of each of the applicable parties under the applicable agreement shall terminate.” By terminating the License Agreement and rights under that agreement, the Termination Agreement terminated Fortress’s license. Although the License Agreement describes the license as “irrevocable” the context clearly refers to the license’s being “irrevocable” by the licensor and does not preclude revocation by mutual agreement. View "Uniloc 2017 LLC v. Google LLC" on Justia Law
CSI Aviation, Inc. v. Department of Homeland Security
CSI was awarded a government contract to provide “[a]ir charter services operated by brokers, and various auxiliary services that will be used to support the contract.” After U.S. Immigration and Customs Enforcement (ICE) canceled various removal flights, CSI sought payment ($40,284,548.89) from the Department of Homeland Security. The Civilian Board of Contract Appeals dismissed the action, concluding that the CSI Terms and Conditions, which include “Cancellation Charges” were not incorporated by reference into the Schedule Contract.The Federal Circuit vacated and remanded. The Schedule Contract expressly incorporates at least one document that unambiguously identifies the CSI Terms and Conditions and makes clear such terms and conditions apply to all operations. CSI’s Offer plainly identified the CSI Terms and Conditions—along with the CSI Commercial Sales Practice attachment, its Pricing Policy, and its Commercial Price List—in the “Pricing” section of its table of contents. View "CSI Aviation, Inc. v. Department of Homeland Security" on Justia Law
Posted in:
Contracts, Government Contracts
Nippon Shinyaku Co., Ltd. v. Sarepta Therapeutics, Inc.
Shinyaku and Sarepta executed an Agreement concerning “a potential business relationship relating to therapies for the treatment of Duchenne Muscular Dystrophy.” During the Agreement’s term the parties would “not directly or indirectly assert or file any legal or equitable .. claim or otherwise initiate any … form of legal or administrative proceeding against the other Party . . . in any jurisdiction … concerning intellectual property in the field of Duchenne Muscular Dystrophy,” including “patent infringement litigations, declaratory judgment actions, patent validity challenges” before the U.S. Patent and Trademark Office (PTO) or Japanese Patent Office, and reexamination proceedings before the PTO. A forum selection, governing intellectual property disputes between the parties after the term’s expiration named the District of Delaware. The term ended in June 2021; the two-year forum selection clause took effect. That same day, Sarepta filed seven Patent Trial and Appeal Board petitions for inter partes review (IPR). Shinyaku filed suit in the District of Delaware asserting breach of contract (alleging that the IPR petitions violated the forum selection clause), declaratory judgment of noninfringement and invalidity concerning Sarepta’s patents, and infringement of Shinyaku’s patents.The Federal Circuit directed that the district court enter an injunction, requiring Sarepta to withdraw the petitions. The plain language of the forum selection clause resolved the dispute. View "Nippon Shinyaku Co., Ltd. v. Sarepta Therapeutics, Inc." on Justia Law
PlasmaCAM, Inc. v. CNCElectronics, LLC
PlasmaCAM sued CNCElectronics for infringing the 441 patent, for which Plasmacam has an exclusive license. In 2019, the parties notified the district court that they had settled the case. When the parties met to draft a formal agreement, however, it became evident that they interpreted the settlement differently, and further negotiations resulted. The parties eventually advised the district court that they had reached a complete agreement. The district court granted the motion to enforce Plasmacam’s version of that agreement and ordered CNC to execute it. The Federal Circuit reversed after holding that the district court order to execute the settlement agreement constituted either an appealable injunction or a final judgment. The court concluded that CNC’s version of the agreement accurately reflects the parties’ understanding. View "PlasmaCAM, Inc. v. CNCElectronics, LLC" on Justia Law