Articles Posted in Government Contracts
by
The United States Army Corps of Engineers awarded the company a contract for construction of a government hospital at Fort Benning. Two rival bidders each filed a bid protest with the Government Accountability Office, which recommended that the contract be re-procured without the company's participation. The GAO found organizational conflict of interest, focusing on the potential for access to nonpublic information and had concluding that the company had access to special knowledge of the Army's requirements that would give unfair advantage. The Army announced that it would follow the GAO recommendation and terminated the contract. The Court of Claims ordered reinstatement and the Federal Circuit affirmed. The Claims Court applied the correct standard of review in concluding that the termination was unreasonable. Th GAO identified no facts to indicated that the company actually had access to specific, sensitive information.

by
The U.S. Department of Energy breached its agreement to accept spent nuclear fuel from nuclear power utilities, including plaintiff, a Wisconsin power cooperative, no longer in operation. Plaintiff maintains 38 metric tons of spent uranium on its property. Had DOE not breached the agreement, the material would have been removed in 2006. Plaintiff joined a consortium of 11 utilities to develop a private repository. The district court awarded about $37.6 million: $16.6 million for maintaining the fuel on-site from 1998 to 2006, $12 million for investment in the consortium, and $6.1 million for various overhead costs associated with mitigation. The Federal Circuit vacated in part. The claims court properly determined that plaintiff was entitled to damages for the entire period, 1999-2006; properly awarded overhead; properly offset the consortium costs; but should have limited the award with respect to the consortium to expenses incurred for mitigation.

by
The Department of Justice issued a request for quotations for an automated recruiting and staffing system, providing that conflicting provisions would be considered as exceptions to the terms of the RFQ, and noting that any exceptions could adversely impact the evaluation rating. Plaintiff's bid included exceptions relating to confidentiality of data and how payments would be made, among other matters. Plaintiff's program obtained a higher score on a performance test. The DOJ disqualified plaintiff's bid and accepted intervenor's bid, stating that plaintiff's slight technical advantage did not justify the higher price and that plaintiff's exceptions were unacceptable. The government accountability office, claims court, and Federal Circuit upheld the decision. The contracting officer was not required to engage in discussions about the exceptions before disqualifying the bid and acted rationally in disqualifying the bid. The officer was entitled to rely on a certification of compliance with RFQ terms for the bid that was accepted and rationally accepted that bid.