Harmonia Holdings Group, LLC v. United States
U.S. Customs and Border Protection (CBP) controls and monitors traffic at the borders, including the flow of vehicles, cargo, and people. CBP’s Cargo Systems Program Directorate (CSPD) manages a commercial trade processing system, the Automated Commercial Environment (ACE), which provides automated tools and information for making admissibility decisions before shipments reach U.S. borders and supports cargo revenue collection. ACE “is not a single operating system but a collection of applications built on diverse multivendor technological platforms.” In 2018, CBP issued a solicitation requesting quotes for “application development and operation and maintenance support services” as part of CSPD’s effort to develop and support cargo systems applications. Harmonia submitted an unsuccessful pre-award agency-level protest to CBP concerning amendments to the solicitation and CBP’s limitation of bid revisions.The Claims Court rejected Harmonia’s subsequent suit on the Administrative Record. The Federal Circuit reversed in part. The Claims Court erred in determining that Harmonia waived its right to assert before the court the same challenges that it asserted in its pre-award protest. The Federal Circuit vacated a holding that CPD did not act in an arbitrary or capricious manner in evaluating Harmonia’s proposal and in making an award decision. The Claims Court must determine the merits of Harmonia’s pre-award protest and what relief, if any, Harmonia is entitled to based on that protest. View "Harmonia Holdings Group, LLC v. United States" on Justia Law
Posted in:
Government Contracts
JKB Solutions and Services, LLC v. United States
In 2015, JKB and the Army entered into a three-year indefinite-delivery, indefinite-quantity contract. JKB agreed to provide instructional services up to 14 classes per year. The contract incorporates Federal Acquisition Regulation (FAR) 52.212-4, which includes a termination for convenience clause for the government, and incorporates Defense Federal Acquisition Regulation Supplement (DFARS) 252.216-7006, which requires all supplies and services furnished under the contract to be ordered by issuance of delivery or task orders. The Army issued three year-long task orders, each listing one lot of training-instructor services, the price per class, and a total price corresponding to the price of 14 classes. Each year, the Army used JKB for fewer than 14 classes and paid for each class actually taught, refusing to pay the total price listed in the task orders.JKB sued for breach of contract. The Claims Court ultimately granted the government summary judgment based on FAR 52.212-4 and the doctrine of constructive termination for convenience. The Federal Circuit vacated. FAR 52.212-4 governs the termination of commercial item contracts for the government’s convenience; it does not apply to service contracts, such as the contract at issue. On remand, the Claims Court may consider whether the “Christian doctrine” applies to incorporate a termination for convenience clause and whether the doctrine of constructive termination for convenience applies. View "JKB Solutions and Services, LLC v. United States" on Justia Law
Posted in:
Contracts, Government Contracts
Triple Canopy, Inc. v. Secretary of the Air Force
Triple Canopy, a private security company, had six fixed-price contracts for security services in Afghanistan, awarded by the Department of Defense. Each contract required that Triple Canopy comply with local law and incorporated Federal Acquisition Regulation 52.229-6, which states: [T]he contract price shall be increased by the amount of any after-imposed tax or of any tax or duty … if the Contractor states in writing that the contract price does not include any contingency for such tax and if liability for such tax, interest, or penalty was not incurred through the Contractor’s fault, negligence, or failure to follow instructions of the Contracting Officer or to ... take all reasonable action to obtain exemption." After repeatedly seeking exemptions, Triple Canopy paid a penalty ($430,994.97) that the Afghan government imposed based on the company having more than 500 employees.Within six years of making payment, Triple Canopy submitted claims. The Armed Services Board of Contract Appeals denied the claims as untimely, 41 U.S.C. 7103(a)(4)(A).The Federal Circuit reversed. Triple Canopy’s claims did not accrue until July 6, 2011, when the Afghan government responded to Triple Canopy’s April 8, 2011 appeal. Triple Canopy’s June 6, 2017 claim submission was within the six-year limitations period Triple Canopy had to comply with the requirement that it “take all reasonable action” to obtain “exemption” from the assessment, which meant appealing the assessment. View "Triple Canopy, Inc. v. Secretary of the Air Force" on Justia Law
Posted in:
Government Contracts
DynCorp International, LLC v. United States
In 2017 the Army issued a logistics support services solicitation, to award several indefinite-delivery, indefinite-quantity contracts—each covering services among six geographic commands, plus Afghanistan. Contracting officers often must discuss deficiencies and significant weaknesses in proposals with offerors before proposals are final. When an offeror proposes a price that is unreasonably high, the government must discuss that unreasonableness with the offeror, potentially giving it a chance to revise its proposal. If the price is too high yet not unreasonable, the government need not discuss it. As a result. an offeror whose initial proposal is unreasonably priced may fare better than one whose is not. Six firms sought to perform the Army’s logistics work. DynCorp lost. Its prices were higher than the others; its proposed technical approach was worse. After balancing four proposal-evaluation factors, none of which DynCorp was best on, the Army went with other offerors.The Federal Circuit affirmed the dismissal of DynCorp’s bid protest, rejecting an argument that the price it gave the Army was so high as to be unreasonable—and that the Army should have concluded as much and given it the opportunity to revise its proposed approach. The court found no error in the Army’s price-reasonableness analysis. View "DynCorp International, LLC v. United States" on Justia Law
Posted in:
Government Contracts
Shell Oil Co. v. United States
In 1942-1943, the government contracted with the Oil Companies to rapidly expand aviation gas (avgas) production facilities and sell vast quantities of avgas to the government with an artificially low profit margin. The government assumed certain risks, agreeing to reimburse “any new or additional taxes, fees, or charges” which the Companies “may be required by any municipal, state, or federal law ... to collect or pay by reason of the production, manufacture, sale or delivery of the [avgas].” The increased production led to increased amounts of acid waste that overwhelmed existing reprocessing facilities. The Companies contracted to dispose of the acid waste at the McColl site in Fullerton, California.In 1991, the United States and California sued under the Comprehensive Environmental Response, Compensation, and Liability Act, 42 U.S.C. 9601, seeking to require the Companies to pay cleanup costs. The Ninth Circuit held that the government was 100% liable for the cost of cleaning up the benzol waste (about 5.5% of the waste) at the McColl site. The Companies have borne nearly all of the clean-up costs incurred since 1994; they submitted a contract termination claim, seeking reimbursement. The Claims Court ultimately found the government liable for all cleanup costs at the McColl site and awarded the Companies $99,509,847.32 for costs incurred through November 2015. The government paid. Remediation at McColl remains ongoing. The Companies sought damages incurred after November 2015. The Federal Circuit affirmed that the government is liable for those costs plus interest, rejecting arguments that res judicata bars the claims and that the Claims Court did not have jurisdiction under the Contract Settlement Act of 1944. View "Shell Oil Co. v. United States" on Justia Law
Asset Protection and Security Services, L.P. v. United States
ICE issued a solicitation for the provision of detention, food, and transportation at its Florence Detention Center. Asset was the incumbent contractor. ICE responded "yes" to, “Arizona charges 4.5% ‘business tax’; will the Federal Government issue a tax exemption certificate to the successful offeror?” Asset’s initial proposal indicated that “[s]ales taxes were not charged” based on that answer. ICE selected Akima's proposal. Asset filed a bid protest. ICE took voluntary corrective action and issued Amendment 17; Amendment 19 subsequently clarified that ICE “CANNOT delegate its tax-exempt status” and instructed that offerors review their proposals and provide their best and final prices. Asset responded that it had reviewed Amendment 19 and that its proposal did not require revision but did not remove the tax-exempt language from its proposal. ICE again clarified the tax-exempt status question via Amendment 20. Asset again responded that it did not need to amend its proposal but the tax-exempt certificate language remained. ICE ultimately selected Akima, concluding that Asset was ineligible for the award because the tax-exempt certificate language rendered its proposal a contingent price. Asset filed another bid protest, disputing ICE’s best-value analysis. The GAO agreed that ICE improperly determined that Asset’s bid contained contingency pricing but concluded that Asset “was not prejudiced” because ICE’s best-value analysis was “reasonable,”The Claims Court concluded that Asset lacked standing to bring the bid protest. The Federal Circuit affirmed. Asset’s proposal was non-responsive to the requirements of the Solicitation, as explicitly amended, making it ineligible for the award. View "Asset Protection and Security Services, L.P. v. United States" on Justia Law
Posted in:
Contracts, Government Contracts
Harmonia Holdings Group, LLC v. United States
The Census Bureau issued a request for quotations seeking statistical analysis system and database programming support services. The Bureau intended to issue a time and materials task order, set aside for women-owned small businesses; the contract award would be made on a best-value basis, considering price and four nonprice factors. The Bureau’s technical evaluation team assigned Harmonia’s proposal nine strengths, no weaknesses, and two risks under factor one, the technical factor; its proposals to cross-train its development staff and to introduce an extract, transform, and load (ETL) automation tool could provide efficiencies but Harmonia’s proposed cross-training and use of an ETL automation tool could result in delays in contract performance. The contracting officer found no meaningful differences in the Harmonia and Alethix proposals with respect to factors two, three, and four; the tradeoff analysis was rooted in the technical factor: The Bureau awarded Alethix the contract.Harmonia filed a protest, challenging the technical evaluation, alleging that the contracting officer violated 48 C.F.R. 19.301-1(b) by failing to refer Alethix to the Small Business Administration for a size determination, and challenging the best-value determination, The Federal Circuit affirmed the Claims Court in granting the government judgment on the administrative record with respect to Counts I and III and dismissing Count II for failure to exhaust administrative remedies. Harmonia had not availed itself of the SBA’s procedures for bringing a size protest. View "Harmonia Holdings Group, LLC v. United States" on Justia Law
Posted in:
Government & Administrative Law, Government Contracts
Conway v. United States
When a Colorado court ordered Colorado Health Insurance Cooperative into liquidation, the government owed Colorado Health $24,489,799 for reinsurance debts under the Patient Protection and Affordable Care Act (ACA), 42 U.S.C. 18061. The reinsurance program, which only lasted three years, collected yearly payments from all insurers and made payments to insurers of particularly costly individuals that year. Colorado Health owed the Department of Health and Human Services $42,000,000 for debts under ACA’s risk adjustment program, which charges insurers of individuals who had below-average actuarial risk and pays insurers of individuals who had above-average actuarial risk. The government attempted to leapfrog other insolvency creditors through offset, rather than paying its debt and making a claim against Colorado Health’s estate as an insolvency creditor.The Federal Circuit affirmed the Claims Court in ordering the government to pay. Neither state nor federal law affords the government a right to offset. Colorado law concerning the liquidation of insurance companies is limited to offsetting debts and credits in contractual obligations. ACA does not preempt Colorado insolvency law; a “Netting Regulation” is directed to an ancillary issue, payment convenience. The government has not shown a “significant conflict between an identifiable federal policy or interest and the operation of state law.” View "Conway v. United States" on Justia Law
NOAA Maryland, LLC v. General Services Administration
GSA leased a building from NOAA’s predecessor; the annual rent includes agreed “[b]ase year taxes.” GSA must compensate NOAA for “any increase in real estate taxes during the lease term over the amount established as the base year taxes” and defines “real estate taxes” as “only those taxes, which are assessed against the building and/or the land upon which the building is located, without regard to benefit to the property, for the purpose of funding general Government services. Real estate taxes shall not include, without limitation, general and/or special assessments, business improvement district assessments, or any other present or future taxes or governmental charges that are imposed upon the Lessor or assessed against the building and/or the land upon which the building is located.In 2016, NOAA asked GSA to reimburse it for the Stormwater/Chesapeake Bay Water Quality tax, the Washington Suburban Transit Commission tax, the Clean Water Act Fee, and a Supplemental Education Tax. All four appear on the consolidated tax bill. The clean water tax, effective in 2013, is collected for the Watershed Protection and Restoration Fund, “in the same manner as County real property taxes and [has] the same priority, rights, and bear[s] the same interest and penalties, and [is] enforced in the same manner as County real property taxes.”GSA denied the claim. The Civilian Board of Contract Appeals held that the lease provision excludes all taxes enacted after the date of the lease, even if those taxes meet expressly stated criteria for being a real estate tax. The Federal Circuit reversed. Under ordinary interpretive principles, a real estate tax qualifies under the Lease provision whenever it satisfies the three criteria of the first sentence. View "NOAA Maryland, LLC v. General Services Administration" on Justia Law
Columbus Regional Hospital v. United States
In 2008, severe storms hit Indiana. Columbus Hospital sustained significant damage. President Bush authorized FEMA assistance through disaster grants under the Stafford Act, 42 U.S.C. 5121–5206. The state agreed to be the grantee for all grant assistance, with the exception of assistance to individuals and households. FEMA reserved the right to recover assistance funds if they were spent inappropriately or distributed through error, misrepresentation, or fraud. Columbus apparently submitted its request directly to FEMA, instead of through the state. FEMA approved Columbus projects, totaling approximately $94 million. Funds were transmitted to Columbus through the state. In 2013, the DHS Inspector General issued an audit report finding that Columbus had committed procurement violations and recommended that FEMA recover $10.9 million. FEMA reduced that amount to $9,612,831.19 and denied Columbus’s appeal. Columbus did not seek judicial review. FEMA recovered the disputed costs from Columbus in 2014.In 2018, Columbus filed suit, alleging four counts of contract breach and illegal exaction. The Claims Court dismissed Columbus’s illegal exaction claim, holding that Columbus did not have a property interest in the disputed funds and that FEMA’s appeal process protected Columbus’s rights to due process, and dismissed Columbus’s contract-based claims, finding that Columbus had no rights against FEMA under that contract or otherwise. The Seventh Circuit affirmed the dismissal of the illegal exaction and express and implied contract claims. The court vacated the dismissal of the third-party beneficiary contract claim. View "Columbus Regional Hospital v. United States" on Justia Law