Justia U.S. Federal Circuit Court of Appeals Opinion Summaries

Articles Posted in Government Contracts
by
The VA sought to procure cable gun locks with information about its suicide prevention line imprinted on the lock body, on a label attached to the cable, and an accompanying wallet card. VA submitted a requisition form to the Government Publishing Office (GPO), which issued an invitation for bids, with unrestricted competition. In a bid protest, the Government Accountability Office found that the Veterans Benefits Act (VBA), 38 U.S.C. 8127(i), applied. VA submitted a revised requisition. VA maintains a database of all verified Service-Disabled Veteran-Owned Small Businesses (SDVOSBs). The GPO’s contracting officer concluded that the GPO was obligated to employ unrestricted competitive bidding without a Rule of Two analysis. The Rule of Two requires that when two or more verified and capable SDVOSBs are identified, the acquisition must be set-aside for SDVOSBs, provided the contracting officer has a reasonable expectation that two or more verified SDVSOBs will submit offers and that the award can be made at a reasonable price. The contracting officer stated that the GPO would “leverage the VA database" to ensure that verified firms received an opportunity to bid.The Claims Court dismissed a pre-award bid protest, reasoning that the solicitation fell within the printing mandate, 44 U.S.C. 501, which requires that governmental "printing, binding, and blank-book work” be done at the GPO; that the VA adequately explained its decision to employ the GPO; and that the VA had met its obligation to secure GPO compliance “to the maximum extent feasible” with the Rule of Two. The Federal Circuit reversed. The printing mandate applies only to the production of written or graphic published materials; the solicitation at issue does not involve “printing.” View "Veterans4You, Inc. v. United States" on Justia Law

by
BGT contracted with the Navy to construct and deliver a generator. The Navy agreed to supply but failed to deliver an exhaust collector and engine mounts (government-furnished equipment "GFE"). Consistent with Federal Acquisitions Regulations (FAR), the contract provides that the Navy “shall consider” an equitable adjustment if it does not deliver the GFE; gives the Navy the right to modify its GFE commitments; and provides that the Navy “shall consider” an equitable adjustment if it modifies those GFE commitments. It requires that equitable adjustments be made according to 48 C.F.R. 52.243-1. The contract also incorporates a clause from outside FAR, providing that no statement or conduct of government personnel shall constitute a change and that the contractor shall not comply with any order, direction, or request of government personnel unless it is issued in writing and signed by the Contracting Officer. The Navy accepted the completed generator but rejected BGT’s request for an equitable adjustment.The Claims Court dismissed BGT’s subsequent lawsuit, finding that BGT had contractually waived its claims of constructive change through ratification, official change by waiver, and breach for failure to award an equitable adjustment and insufficiently alleged a breach of the implied duty of good faith and fair dealing. The Federal Circuit affirmed the dismissal of the good faith and fair dealing claim but vacated the dismissal of the remaining claims. Even assuming that the contracting officer is not chargeable with having ordered the withdrawal of the GFE, there is an alternate pathway to relief. If relief under the standard FAR provisions were not available, the government could avoid liability for reneging on its GFE commitments in any case simply by withdrawing GFE without written notice from the contracting officer. View "BGT Holdings LLC v. United States" on Justia Law

by
Boeing entered into contracts with the Air Force that require Boeing to deliver technical data with “unlimited rights,” meaning that the government has the right to “use, modify, reproduce, perform, display, release, or disclose [the] technical data in whole or in part, in any manner, and for any purpose whatsoever, and to have or authorize others to do so.” Notwithstanding the government’s unlimited rights, Boeing retains ownership of any technical data it delivers under the contracts.Boeing marked each submission to the Air Force with a legend that purports to describe Boeing’s rights in the data with respect to third parties. The government rejected Boeing’s technical data, finding that Boeing’s legend is a nonconforming marking because it is not in the format authorized by the contracts under the Defense Federal Acquisition Regulation Supplement, Subsection 7013(f). Boeing argued that Subsection 7013(f) is inapplicable to legends that only restrict the rights of third parties. The Armed Services Board of Contract Appeals agreed with the government.The Federal Circuit vacated. Subsection 7013(f) applies only in situations when a contractor seeks to assert restrictions on the government’s rights. The court remanded for resolution of an unresolved factual dispute remains between the parties regarding whether Boeing’s proprietary legend, in fact, restricts the government’s rights. View "Boeing Co. v. Secretary of the Air Force" on Justia Law

by
Dr. Braun worked at the National Institutes of Health (NIH) for almost 32 years as a research doctor with a specialty in neurological disorders. He obtained tenured status in 2003. In 2016, the NIH, which is located within the U.S. Department of Health and Human Services, removed Dr. Braun from his position after an audit revealed that his records were incomplete for all but 9% of the human subjects who had participated in his research over the course of six years.The Merit Systems Protection Board rejected Braun’s argument that an NIH policy required de-tenuring of tenured scientists (which NIH had not done in his case) before they could be removed for performance-related reasons and that the NIH committed certain other errors. The Board reasoned that the cited NIH policy allows removal “for cause” without de-tenuring. The Federal Circuit affirmed. The “for cause” provision was properly applied to this case. The evidence permitted the conclusions that Dr. Braun, “over a long period of time,” failed to a “dramatic and disturbing” degree, to comply with protocol requirements that exist “for the safety of the patients and the credibility of the research.” There was no denial of due process. View "Braun v. Department of Health and Human Services" on Justia Law

by
The Joint Enterprise Defense Infrastructure Cloud procurement is directed to the long-term provision of enterprise-wide cloud computing services to the Defense Department. Its solicitation contemplated a 10-year indefinite-delivery, indefinite-quantity contract with a single provider. The JEDI solicitation included “gate” provisions that prospective bidders would be required to satisfy, including that the contractor must have at least three existing physical commercial cloud offering data centers within the U.S., separated by at least 150 miles, providing certain offerings that were “FedRAMP Moderate Authorized” at the time of proposal (a reference to a security level). Oracle did not satisfy the FedRAMP Moderate Authorized requirement and filed a pre-bid protest.The Government Accountability Office, Claims Court, and Federal Circuit rejected the protest. Even if Defense violated 10 U.S.C. 2304a by structuring the procurement on a single-award basis, the FedRAMP requirement would have been included in a multiple-award solicitation, so Oracle was not prejudiced by the single-award decision. The FedRAMP requirement “constituted a specification,” not a qualification requirement; the agency structured the procurement as a full and open competition. Satisfying the gate criteria was merely the first step in ensuring that the Department’s time was not wasted on offerors who could not meet its minimum needs. The contracting officer properly exercised her discretion in finding that the individual and organizational conflicts complained of by Oracle did not affect the integrity of the procurement. View "Oracle America Inc. v. United States" on Justia Law

by
KBR contracted with the government to provide trailers to house coalition personnel at military camps in Iraq. KBR claimed that the government breached the contract by failing to provide “force protection” to the trucks delivering the trailers to the military camps. KBR sought to recover payments made to its subcontractor, Kuwaiti, for costs caused by the government’s alleged breach. The administrative contracting officer in large part denied the claim. The Armed Services Board of Contract Appeals found that KBR was not entitled to any additional recovery. The Federal Circuit affirmed. The Board properly determined that KBR’s costs had not been shown to be reasonable. The court did not reach the question of whether the government breached the “force protection” provision of the contract. The burden is on the contractor to establish the reasonableness of its costs; there is no presumption of reasonableness nor any presumption that a contractor is entitled to reimbursement “simply because it incurred . . . costs.” View "Kellogg Brown and Root Services, Inc. v. Secretary of the Army" on Justia Law

by
The Federal Highway Administration (FHA) issued a solicitation for the "Deweyville" project, consisting of reconstructing approximately 12 miles of road running through Alaska's Tongass National Forest. The FHA provided a Waste Site Report, which identified sites that a contractor could use to dispose of waste materials and provided access to the “Categorical Exclusion,” prepared under the National Environmental Policy Act, 42 U.S.C. 4321–70.2, which stated that waste sites are expected to be sourced at existing quarries identified in the Waste Site Report. The solicitation placed responsibility for licenses and permits on the contractor, including Clean Water Act permits, 33 U.S.C. 1344, and purchasing wetland mitigation credits. Kiewit’s successful bid included approximately $1,000,000 for wetland mitigation fees. Kiewit requested an equitable adjustment for the cost of purchasing mitigation credits for the wetlands it encountered at government-designated waste sites. The Claims Court upheld the denial of that request.The Federal Circuit reversed. The contract documents dictate that, unless a contractor decided to expand the government-designated waste sites, “[n]o further analysis of the environmental impacts of” such sites would be necessary. That the FHA, during the NEPA process, had already assessed the project’s effects on wetlands bolstered Kiewit’s reasonable conclusion that it would not need to conduct further wetlands analysis at designated waste disposal areas. Kiewit reasonably interpreted the documents to mean what they say—that no further environmental impacts analysis would be required if a contractor chose to dispose of waste at government-designated sites. The FHA effected a constructive contract change when it required Kiewit to perform wetland delineation at those sites. View "Kiewit Infrastructure West Co. v. United States" on Justia Law

by
In the Patient Protection and Affordable Care Act (ACA), Congress directed each state to establish an online exchange through which insurers may sell health plans if the plans meet certain requirements. One requirement is that insurers must reduce the “cost-sharing” burdens—such as the burdens of making co-payments and meeting deductibles—of certain customers. When insurers meet that requirement, the Secretary of Health and Human Services shall reimburse them for those cost-sharing reductions, 42 U.S.C. 18071(c)(3)(A). In October 2017, the Secretary stopped making reimbursement payments, due to determinations that such payments were not within the congressional appropriation that the Secretary had, until then, invoked to pay the reimbursements. Sanford, a seller of insurance through the North Dakota, South Dakota, and Iowa exchanges, and Montana Health, a seller through the Montana and Idaho exchanges, sued.The trial courts granted the insurers summary judgment, reasoning that the ACA reimbursement provision is “money-mandating” and that the government is liable for damages for its failure to make reimbursements for the 2017 reductions. The court did not reach the contract claim in either case. The Federal Circuit affirmed, citing the Supreme Court’s 2020 “Maine Community,” addressing a different payment-obligation ACA provision. Maine Community indicates that the cost-sharing-reduction reimbursement provision imposes an unambiguous obligation on the government to pay money; that obligation is enforceable in the Claims Court under the Tucker Act, 28 U.S.C. 1491(a)(1). View "Sanford Health Plan v. United States" on Justia Law

by
The Patient Protection and Affordable Care Act (ACA), 124 Stat. 119, directed each state to establish an online exchange through which insurers may sell health plans that meet certain requirements. Insurers must reduce the “cost-sharing” burdens, such as co-payments and deductibles, of certain customers. When insurers meet that requirement, the Secretary of Health and Human Services (HHS) shall reimburse them for the required cost-sharing reductions, 42 U.S.C. 18071(c)(3)(A). In October 2017, the Secretary stopped making reimbursement payments, due to determinations that such payments were not within the congressional appropriation that the Secretary had invoked to pay the reimbursements. Insurers sued.The Federal Circuit affirmed summary judgment in favor of the insurers on liability, reasoning that the ACA reimbursement provision is “money-mandating” and that the government is liable for damages. The court cited the Supreme Court’s 2020 “Maine Community,” addressing a different ACA payment-obligation as indicating that the cost-sharing-reduction reimbursement provision imposes an unambiguous obligation on the government to pay money; that obligation is enforceable through a damages action under the Tucker Act, 28 U.S.C. 1491(a)(1). The court remanded the issue of damages. The government is not entitled to a reduction in damages with respect to cost-sharing reductions not paid in 2017. As to 2018, the Claims Court must reduce the insurers’ damages by the amount of additional premium tax credit payments that each insurer received as a result of the government’s termination of cost-sharing reduction payments. View "Community Health Choice, Inc. v. United States" on Justia Law

by
After the U.S. invasion of Iraq, Agility was awarded a contract for support of staging area operations (PCO Contract). Under the Contract, the Coalition Provisional Authority (CPA) could issue individual task orders to Agility. Funds obligated under the contract were sourced from the Development Fund for Iraq (DFI). The CPA controlled the DFI, which consisted of Iraqi money. The Contract provided that “[n]o funds, appropriated or other, of any Coalition country are or will be obligated under this contract” and recognize[d] that a transfer of authority from the CPA to the interim Iraqi Governing Council (IIG) would occur in June 2004. The contracting parties were the CPA and Agility. The Contract expressly preserved the right of the United States to assert claims against Agility. A Contract amendment provided that any claim Agility had after the transfer to IIG could not be brought before the Armed Services Board of Contract Appeals but could only be brought in an Iraqi court. The U.S. Army was designated as the administrator of the PCO contract.In 2010, following an audit of the PCO Contract, the Army contracting officer sent demand letters for overpayments allegedly made under 12 task orders. The Claims Court upheld the offsets, holding that the United States (rather than Iraq) was owed the alleged overpayment and the United States was authorized to offset the alleged overpayment. The Federal Circuit in part and vacated in part. The Claims Court did not evaluate the merits of the offset determination nor the procedures required by law. View "Agility Public Warehousing Co. v. United States" on Justia Law